In normal circumstances, this is the appeal process for applications for local development determined under delegated powers.
Submitting a Notice of Review
The 'Notice of Review', can be served by the applicant on the planning authority to seek review of a decision taken by the appointed officer under delegated powers.
The Local Review Body (LRB) consists of at least three elected members. There is also a planning advisor and legal advisor, and the LRB may request advice from experts on particular subjects if considered necessary. The process must be fair and transparent.
A Notice of Review can sent by the applicant within the following time periods:
- Within 3 months of the decision of the application; or
- If the application has not been determined, the date of expiry of the period allowed for determining the application. The date of expiry is 2 months after the application has been validated; or the day after the agreed ‘extension of time’ date, if further time to determine the application has been agreed between the applicant and the Planning Authority.
Applicants must include reasons for requiring the review, the preferred method of review, the matters to be raised and documents to be used. Further information will only be accepted if requested by the LRB.
The Local Review Body
Upon receipt of the Notice of Review, the LRB will make interested parties aware - statutory consultees and those that initially commented on the application. 14 days are allowed for further representations from those interested parties. The applicant may see these and make further comment.
The LRB can consider whether to hold a pre-examination meeting. Notice would be given to the interested parties, as they consider reasonable. At the pre-examination meeting, the LRB may request further information by way of written submissions or hearings and/or site visit; decide matters to be discussed; and the procedure to follow. Regulations cover these matters and how to deal with the new evidence.
If the LRB does not choose to have a pre-examination meeting, it can proceed to determine the review. In normal circumstances, meetings must be held in public. There is no automatic right for the applicant or others to be make oral representation. The method of determination (i.e. written submissions or a hearing) is at the discretion of the LRB.
Planning Development Management Committee, Local Review Body and Pre-application Forum meetings are held in the Council Chamber and the public can attend in person but cannot make verbal representations to the committee. The meetings are also streamed live on the Council’s website. Please visit our committee pages for details on Committee dates, minutes and agendas (live stream accessible from the Agenda frontsheet) and our webcast library for weblinks to the recordings.
A Decision notice will thereafter be issued and this must include the issues considered, and the reasons for their decision. The Local Review Body has powers to uphold the decision by the officers, or overturn the decision.
If the applicant wishes to question the validity of the decision, application may be made to the Court of Session within 6 weeks.
In the situation where an application has not been determined within 2 months or any longer period which has been agreed in writing by the parties, a 'Notice of Review' has been served by the applicant, but the review has not been carried out within 3 months, the applicant can appeal to the Scottish Ministers.